Valmet Hakkila Office Campus

Parmaco has delivered a 2,382 m² office for Valmet’s Flow Control business under a rental agreement. In use since August 2026 in Vantaa, Finland, the building combines 32 steel modules relocated from a former school with four new modules. The project demonstrates how existing building assets can be redeployed to serve private-sector office customers.

Hakkila demonstrates how Parmaco can bring an existing building back into rental use for a customer in a different sector. The project connects demand for private-sector offices with a reusable building asset, extending its commercial life through relocation and repurposing.

  • Office
  • Mäntytie 18, 01830 Nurmijärvi
  • 2026
  • 4753 m²
  • 2 floors

“Our collaboration with Parmaco has run smoothly throughout the project. Although the project involved reusing an existing building, the premises have been successfully reconfigured to meet Valmet’s needs, resulting in a modern and functional office environment. Feedback from our employees after the first few months in the new office has been positive, which is particularly important to us.”

Timi Nieminen, Director, Operations Footprint Development, Valmet

A new workplace at the Hakkila campus

Valmet needed modern premises at its Hakkila factory campus to replace an office building that had reached the end of its useful life. Parmaco identified a recently vacated school building in Riihikallio, Tuusula, less than ten kilometres away, whose dimensions suited Valmet’s requirements.

The building was relocated and redesigned for office use. Workspaces and meeting rooms are complemented by a staff restaurant, auditorium and gym, with the layout shaped around Valmet’s operations and its employees’ daily needs.

Rental premises without investment in building ownership

Valmet rents the office from Parmaco, securing premises tailored to its operations without investing in ownership of the building. Parmaco is responsible for the building’s maintenance and condition throughout its lifecycle.

The building can also be expanded, reduced in size, reconfigured or relocated as needs change.

32 reused modules and six days of assembly

All 32 modules from the former school were reused, with four new modules added to complete the building.

The building permit was granted in March 2026, and the modules were assembled on site in six days in April. The wider project also included redesign, conversion and finishing work, and the completed office entered use in August.

A lower carbon footprint through reuse

According to the project’s carbon footprint assessment, reusing the modules reduced the construction-stage carbon footprint by 53% compared with an equivalent building made entirely from new steel modules. Over the assessed lifecycle, the carbon footprint is 31% lower.

The project puts circular construction into practice by continuing to use existing structures and limiting the need for new ones.

The Hakkila office demonstrates how a circular approach to construction can meet businesses’ changing space requirements with speed and flexibility.

Read more: Circularity in practice: Valmet’s Hakkila campus takes a step towards net zero (in Finnish)